Innovo Property Group

24-02 49th Ave. | Roof Replacement

Turi Management Corp partnered with IPG for the completion of a total roof replacement covering 100,000 Sq. Ft. Turi provided a design assist to budget and plan several roof replacement options after which a new, R33 Built Up Roof membrane with tapered insulation to new roof drains was selected. During construction, material shortages forced delays for the installation of the roof insulation risking an overall delay in completion of the project. Turi worked with the roof consultant and manufacturer to substitute the tapered insulation with insulated poured and tapered concrete, which was readily available. The solution allowed for the completion of the project on time, while maintaining the required R33 insulation value.